- EMS ISD Bond Progress
- Maintenance Facility
Maintenance Facility
-
March 2021 Update
- Substantial completition of the facility to be completed in April.
December 2020 Update
- New view of the building from the road.
- Warehouse exterior metal panels are being installed.
November 2020 Update
- The grade beams have been poured and the final grading for the slab pour is in progress.
October 2020 Update
- The framing and pouring of grade beams is in progress.
August/September 2020 Update
- The building site is prepped and mosture conditioning is complete.
July 2020 Update
- The generator pad with electrical tubing is in place within the server room.
- Additional HVAC support has been installed.
May/June 2020 Update
- Network Operations Center to be completed in August.
April 2020 Update
- Network Operations Center (NOC) – Design and ordering of materials in progress
-
March 2021 Construction Photos
The photos above show storage racks, elecrical progress and a walk-in freezer.
-
November 2020 Construction Photos
The final grading for the slab pour is in progress.
-
October 2020 Construction Photos
The framing and pouring of grade beams is in progress.
-
August/September 2020 Construction Photos
The building site is prepped.
-
July 2020 Construction Photos
From left, the generator pad with electrical tubing is in place within the server room. Additional HVAC support has been installed.