- EMS ISD Bond Progress
- Highland MS, Creekview MS & Gililland ES
Highland MS, Creekview MS & Gililland ES
-
Renovations are underway at, l and August 2019 Update:
- Landscaping at Creekview MS is in place.
- Landscaping at Highland MS is being installed.
- The media center, secure vestibule, and new kitchen serving line for students has been completed at Creekview.
- New surfacing of tennis courts and new wind slats has been added at Creekview.
- Tennis court slat installation is complete at Highland.
- Laying of new tile in hallway and media center at Highland.
July 2019 Update:
- Library ceiling grid, lighting, sheetrock, tape and bedding complete.
- Creekview and Highland: Storefront office glass, wall tiling, and wood slats installed in the library collaboration area.
- Creekview and Highland: Gyms have new LED lighting.
- Creekview: new floor tile in place, floors are waxed, new carpet in classrooms, gym floors are sanded.
- Highland: new irrigation system is being installed and wind slats at the tennis courts.
- Gililland: secure door added in the reception area.
May 2019 Update at Creekview & Highland:
- Doorframes have been installed and painted.
- Temporary wall has been added to a separate office area from construction inside the school.
- Ceiling tiles and lighting is complete.
- Finish painting is near completion.
- The aluminum storefront is being installed.
- Finish flooring and protective covering have been installed.
March 2019 Update:
- Finalizing plumbing
February 2019 Update:
- Demolition of existing space is complete.
- Drywall is near completion.
-
March 2020 Construction Photos
-
September 2019 Construction Photos
-
August 2019 Construction Photos
-
July 2019 Construction Photos
-
May 2019 Construction Photos
-
March 2019 Construction Photos