District New Construction Progress
In a presentation to the Board of Education on December 16, 2019, Chief Operations Officer Clete Welch shared updates about Copper Creek Elementary:
- Site work continues.
- The walls for the gymnasium/storm shelter are being constructed off site.
- Ceiling work, tiling, tape and bedding and painting is in progress in the kitchen and serving line.
- Kitchen equipment is being installed.
- Framing and sheetrock work is occurring in the library.